Van Oord Completes Installation Of Belgium’s Largest Offshore Wind Farm

Van Oord successfully installed the last of the in total 44 wind turbines of the Northern offshore wind farm. Achieving this milestone and already delivering renewable energy makes an important contribution to the energy transition.

aeolus_offshore
Image Credits: vanoord.com

Van Oord was contracted as main contractor. The entire scope, from cable installation and burial, installation of the Offshore High Voltage Station (OHVS) to turbine installation, was completed ahead of schedule and in less than 9 months. Van Oord deployed a wide range of equipment at the project, amongst others offshore installation vessel Aeolus, the newest trencher Dig-It and cable-laying vessel Nexus.

The achievement of completing such a complex scope of work in this time frame, is something that all involved on this project can be proud of.

Floren Verweij, Project Manager Van Oord

The 370-megawatt offshore wind farm supplies almost 400,000 households with renewable energy. The Northern offshore wind farm will contribute significantly to Belgium meeting its target of generating 13% of its energy needs from renewable sources by 2020.

Reference: vanoord.com